Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 5 days. B ' s

Activity D on a CPM network has predecessors B and C, and has successor F. D has
duration 5 days. B's earliest finish is 18, while C's is 15. F's late start is 23. Which of
the following is definitely TRUE?
D is critical, and has a slack of five days.
C has slack, and is not critical.
C must be started after B is finished.
B has slack, and is critical.
F is not critical, and has slack.