Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 5 days. B ' s
Activity D on a CPM network has predecessors B and C and has successor F D has
duration days. Bs earliest finish is while Cs is Fs late start is Which of
the following is definitely TRUE?
D is critical, and has a slack of five days.
C has slack, and is not critical.
C must be started after is finished.
B has slack, and is critical.
F is not critical, and has slack.