Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 6 . B ' s

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is18, while C's is 20. F's late start is 26. Which of the following is definitely true?
Part 2
A.
D is critical, and has a slack of two days.
B.
F is critical, and has zero slack.
C.
C is completed before B.
D.
D has no slack but is not critical.
E.
B is a critical activity.