Question: Activity D on a CPM network has predecessors B and C , and has successor F . D has duration 6 . B ' s
Activity D on a CPM network has predecessors B and C and has successor F D has duration Bs earliest finish is while Cs is Fs late start is Which of the following is definitely true?
Part
A
D is critical, and has a slack of two days.
B
F is critical, and has zero slack.
C
C is completed before B
D
D has no slack but is not critical.
E
B is a critical activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
