Question: Activity Dependency Optimistic Most likely Pessimistic A - 5 6 8 B - 3 4 5 C A 2 3 4 D B x-1 x
| Activity | Dependency | Optimistic | Most likely | Pessimistic |
| A | - | 5 | 6 | 8 |
| B | - | 3 | 4 | 5 |
| C | A | 2 | 3 | 4 |
| D | B | x-1 | x = (last digit of your roll no. +4) | x+2 |
| E | B | 1 | 3 | 4 |
| F | - | 8 | 10 | 15 |
| G | E,F | 2 | 3 | 4 |
| H | C,D | 2 | 2 | 2.5 |
- By using three estimates for each activity, find:
- Estimated time 'te'
- Activity standard deviation s
- Draw PERT network after calculating the events estimated times and standard deviations.