Question: Activity Dependency Optimistic Most likely Pessimistic A 5 6 8 B 3 4 5 | 3 4 D B 16-1 6=(+4) 6+2 E B 1

 Activity Dependency Optimistic Most likely Pessimistic A 5 6 8 B

Activity Dependency Optimistic Most likely Pessimistic A 5 6 8 B 3 4 5 | 3 4 D B 16-1 6=(+4) 6+2 E B 1 3 4 F 8 10 15 92 E,F 2 3 4 H C,D 2 2 2.5 1. By using three estimates for each activity, find: [2] 1.1. Estimated time 'te" 1.2. Activity standard deviation s' 2. Draw PERT network after calculating the events' estimated times and standard deviations. [4]