Question: Activity # Description Predecessor Expected Duration ( days) A Create a project plan None 10 B Research of the topic A 2 C Define equipment
Activity # Description Predecessor Expected Duration ( days) A Create a project plan None 10 B Research of the topic A 2 C Define equipment A 1 D Software installations A 1 E Shooting video B,C,D 2 F Editing video E 2 G Test video F 1 H Presentation to the client G 1 I Uploading the video to website H 1