Question: Activity Duration 3. (10 Points) Given the AON network in Figure 2 (following page), determine the ES, EF, LS, LF, Total Float, and Free Float

Activity Duration 3. (10 Points) Given the AON

Activity Duration 3. (10 Points) Given the AON network in Figure 2 (following page), determine the ES, EF, LS, LF, Total Float, and Free Float of each activity. Also, indicate the critical path of the network. (Unlabeled relationships are F2S with O lag.) Use the following legend for filling out the AON network: ES Total Float EF LS Free Float LF Figure 2 SS 5 FF 4 SS 3 J 2 K10 FF 3 I 4 H6 SS 1 FS 7 SS 3 F | 4 FF 3 E 5 G 3 SS 6 C 10 3 4 D9 FS 2 SS 3 A3 SS 3