Question: Activity Duration (days) A B C D E F G 1.5 6 4 0.5 7.5 6.5 3.5 Predecessors None None None A, B C D,




\begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 1.5 & None \\ B & 6 & None \\ C & 4 & None \\ D & 0.5 & A, B \\ E & 7.5 & C \\ F & 6.5 & D, E \\ G & 3.5 & F \end{tabular} \begin{tabular}{|lll|} \hline A & 1.5 & None \\ B & 6 & None \\ C & 4 & None \\ D & 0.5 & A, B \\ E & 7.5 & C \\ F & 6.5 & D,E \\ G & 3.5 & F \\ H & 0.5 & F \\ \hline \end{tabular} a. Choose the correct project network diagram below k Q Oo. Q Q (B) (C) () (c) (11) \begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 1.5 & None \\ B & 6 & None \\ C & 4 & None \\ D & 0.5 & A, B \\ E & 7.5 & C \\ F & 6.5 & D, E \\ G & 3.5 & F \end{tabular} \begin{tabular}{|lll|} \hline A & 1.5 & None \\ B & 6 & None \\ C & 4 & None \\ D & 0.5 & A, B \\ E & 7.5 & C \\ F & 6.5 & D,E \\ G & 3.5 & F \\ H & 0.5 & F \\ \hline \end{tabular} a. Choose the correct project network diagram below k Q Oo. Q Q (B) (C) () (c) (11)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts