Question: Activity Duration (days) Immediate Predecessor A 1 - B 2 A C 3 A D 4 B, C E 5 D F 6 D A

Activity

Duration

(days)

Immediate

Predecessor

A

1

-

B

2

A

C

3

A

D

4

B, C

E

5

D

F

6

D

A project consists of activities A to F. The following table shows durations and precedence relationships of these activities.

Draw a network for this project and answer the following questions: What is the critical path? What is the shortest time to finish this project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!