Question: Activity Duration (days) Immediate Predecessor A 1 - B 2 A C 3 A D 4 B, C E 5 D F 6 D A
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
A project consists of activities A to F. The following table shows durations and precedence relationships of these activities.
Draw a network for this project and answer the following questions: What is the critical path? What is the shortest time to finish this project.