Question: Use the area below the table to draw the network diagram. Draw by hand (very neatly or Ill reject it) or use the Word Shapes

Use the area below the table to draw the network diagram. Draw by hand (very neatly or Ill reject it) or use the Word Shapes to create.

If you hand draw, scan the pages and upload to Blackboard for grade. If you use the Word Shapes, just upload the document for grade.

Exercise 1

Activity

Predecessor(s)

A

-

B

-

C

A

D

B

E

D

F

C

G

E,F

Exercise 2

  1. Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
  2. Using the Enumeration Method list all the network paths with length.

Activity

Details

Duration (days)

Predecessor(s)

A

Dig Holes

3

-

B

Buy Wood

2

Dig Holes

C

Buy Gate

1

Dig Holes

D

Erect Fence

3

Buy Wood

E

Buy Paint

1

Buy Gate

F

Erect Gate

1

Erect Fence, Buy Paint

G

Paint Fence

2

Erect Gate

H

Paint Gate

1

Paint Fence

Exercise 3

  1. Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
  2. Using the Enumeration Method list all the network paths with length.

Activity

Duration (days)

Predecessor(s)

A

2

-

B

2

A

C

4

A

D

1

B

E

3

C,D

F

2

C,D

G

4

E

H

5

F,G

Exercise 4

  1. Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
  2. Using the Enumeration Method list all the network paths with length.

Activity

Duration (days)

Predecessor(s)

A

2

-

B

3

-

C

4

A,B

D

5

C

E

2

D

F

3

D

G

4

E

H

2

F

I

2

G,H

Exercise 5

  1. Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
  2. Using the Enumeration Method list all the network paths with length.

Activity

Duration (days)

Immediate Predecessor

A

5

B

2

A

C

4

A

D

7

A

E

3

B

F

6

B,C

G

8

D,E,F

Exercise 6

  1. Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
  2. Using the Enumeration Method list all the network paths with length.

Activity

Duration (days)

Immediate Predecessor

A

2

-

B

2

A

C

4

A

D

1

B

E

3

C,D

F

2

C,D

G

4

E

H

5

F,G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!