Question: Activity Duration (Days) Predecessor A 10 - B 14 - C 11 A D 5 B E 15 B F 20 B G 8 C
| Activity | Duration (Days) | Predecessor |
| A | 10 | - |
| B | 14 | - |
| C | 11 | A |
| D | 5 | B |
| E | 15 | B |
| F | 20 | B |
| G | 8 | C |
| H | 12 | C, D |
| I | 16 | G |
| J | 10 | H, E |
| K | 21 | H, E |
| L | 6 | H, E |
| M | 9 | I, J, K |
| N | 12 | F, L |
Draw the activity network diagram. Include earliest start date (ESD), latest finish date (LFD) for every event. Label the critical path and activities with slack time. (Explain as well)