Question: Activity Duration (Days) Predecessor A 10 - B 14 - C 11 A D 5 B E 15 B F 20 B G 8 C

Activity

Duration (Days)

Predecessor

A

10

-

B

14

-

C

11

A

D

5

B

E

15

B

F

20

B

G

8

C

H

12

C, D

I

16

G

J

10

H, E

K

21

H, E

L

6

H, E

M

9

I, J, K

N

12

F, L

Draw the activity network diagram. Include earliest start date (ESD), latest finish date (LFD) for every event. Label the critical path and activities with slack time. (Explain as well)