Question: Activity Duration Dependency A 8 B 2 A C 3 A D 10 A E 12 B F 2 B G 2 C,D H 6
| Activity | Duration | Dependency |
| A | 8 |
|
| B | 2 | A |
| C | 3 | A |
| D | 10 | A |
| E | 12 | B |
| F | 2 | B |
| G | 2 | C,D |
| H | 6 | E,F,G |
| I | 5 | E |
| J | 6 | I |
| K | 5 | H |
| L | 3 | G |
| M | 4 | J,K,L |
a) Draw a project network from the table above b)
What activity(s) is a burst activity?
What activity(s) is a merge activity?
What is the length of the project?
What is/are the critical path(s)?
Question 9