Question: Activity Duration Predecessors A 4 B 9 C 10 B D 8 C E 5 C F 4 E G 8 A H 8 D

Activity

Duration

Predecessors

A

4

B

9

C

10

B

D

8

C

E

5

C

F

4

E

G

8

A

H

8

D & F & G

The critical path is 36 weeks long. Management would like us to get this project to 32 or fewer weeks for the least cost. The following crashing options are available. What single or group of crashes will shorten the project for the least cost? Write the activities crashed and the net cost in the text box for the assignment.

Crash

Shorten by weeks

Cost

A

1

1000

B

1

750

C

2

1200

D

1

1000

E

2

1000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!