Question: Activity Duration Predecessors A 4 B 9 C 10 B D 8 C E 5 C F 4 E G 8 A H 8 D
| Activity | Duration | Predecessors |
| A | 4 |
|
| B | 9 |
|
| C | 10 | B |
| D | 8 | C |
| E | 5 | C |
| F | 4 | E |
| G | 8 | A |
| H | 8 | D & F & G |
The critical path is 36 weeks long. Management would like us to get this project to 32 or fewer weeks for the least cost. The following crashing options are available. What single or group of crashes will shorten the project for the least cost? Write the activities crashed and the net cost in the text box for the assignment.
| Crash | Shorten by weeks | Cost |
| A | 1 | 1000 |
| B | 1 | 750 |
| C | 2 | 1200 |
| D | 1 | 1000 |
| E | 2 | 1000 |