Question: Q3: Draw the critical path for the network activities shownbelow. What is the duration of the critical path. ________. Activity Duration ImmediatePredecessors A 4 --
Q3: Draw the critical path for the network activities shownbelow.
What is the duration of the critical path.
________.
Activity Duration ImmediatePredecessors
A 4 --
B 2 A
C 7 --
D 4 A
E 5 B,C,D