Question: Activity Duration (weeks) Activity Duration (weeks) A 2.5 J 4.5 B 3.5 K 2.5 C 2 L 1 D 3 M 2.5 E 1.5 N

 Activity Duration (weeks) Activity Duration (weeks) A 2.5 J 4.5 B

Activity Duration (weeks) Activity Duration (weeks)
A 2.5 J 4.5
B 3.5 K 2.5
C 2 L 1
D 3 M 2.5
E 1.5 N 3.5
F 2 O 1.5
G 4 P 2.5
H 1.5 Q 4.5
I 2

1a. What is the total time required to complete the project if no delays occur?

1b. When do the individual activities need to start and finish (at the latest) to meet this project completion time?

1c. When can the individual activities start and finish (at the earliest) if no delays occur?

1d. Which are the critical bottleneck activities where any delays must be avoided to prevent delaying project completion?

1e. For the other activities, how much delay can be tolerated without delaying project completion?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!