Question: Activity Duration ( weeks ) Immediate Predecessor ( s ) A 2 - B 8 A C 7 A D 7 A E 4 A
Activity Duration weeks Immediate Predecessors
A
B A
C A
D A
E A
F BC
G DE
H FGWhat would be the overall duration of the project if activity D were increased by weeks, from to weeks?
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
