Question: Activity Duration ( weeks ) Immediate Predecessor ( s ) A 2 - B 8 A C 7 A D 7 A E 4 A

Activity Duration (weeks) Immediate Predecessor(s)
A 2-
B 8 A
C 7 A
D 7 A
E 4 A
F 12 B,C
G 9 D,E
H 7 F,GWhat would be the overall duration of the project if activity D were increased by 3 weeks, from 7 to 10 weeks?
27
weeks