Question: Please solve the question with calculation and steps not drawing . what is the minimum duration to finish this project ? , show all the

Please solve the question with calculation and

Please solve the question with calculation and steps not drawing .

what is the minimum duration to finish this project ? , show all the steps clearly

QUESTION 11 Activity Duration (Days) Immediate Predecessor Activities A 2 B 3 A D 5 A&B E 8 C&D D G 2 F H G What is the minimum duration to finish this project? Show all the steps clearly