Question: Activity E has these Estimates for duration: Optimistic = 9 1 days, Most likely = 9 6 days, Pessimistic = 1 0 3 days. What

Activity E has these Estimates for duration: Optimistic =91 days, Most likely =96 days, Pessimistic =103 days. What is the estimated standard deviation for Activity E?
Group of answer choices
1
2
4
16
None of the abov