Question: Activity E has these estimates for duration: Optimistic = 91 days, Most likely = 100 days, pessimistic = 115 days. What is the estimated standard
Activity E has these estimates for duration: Optimistic = 91 days, Most likely = 100 days, pessimistic = 115 days. What is the estimated standard deviation for activity E?
a. 1
b. 2
c. 4
d, 16