Question: Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)-

| Activity | Each Activity Should be Reduced BY (weeks) |
| A | (weeks)- ? |
| B | (weeks)- ? |
| C | (weeks)- ? |
| D | (weeks)- ? |
| E | (weeks)- ? |
| F | (weeks)- ? |
AND What is the total crashing cost ?
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) 2 Precedes B, C E 2 Activity A (start) B E F (end) Crash Cost/Week $370 $120 $240 $140 $450 5 F 2 F 3 Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks durationStep by Step Solution