Question content area
Part 1
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week:
Activity
Duration(weeks)
Precedes
Crash Cost/Week
A(start)
3
B, C
$ 380
B
2
E
$ 130
C
5
F
$ 220
E
2
F
$ 150
F(end)
4
long dash
$ 400
Part 2
Suppose that Rafay is only given 10 weeks(instead of 12) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration.
Part 3Part 4Part 5Part 6
Activity
Each Activity Should be Reduced BY
(weeks)
A
0week(s)
B
1week(s)
C
2week(s)
E
0week(s)
F
0week(s)
Part 7
What is the total crashing cost?$
enter your response here (Enter your response as a whole number.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!