Question: Activity Estimated Duration (in weeks) Preceding Activities Required Reusable Resources Optimistic Most Likely Pessimistic Resource-1 Resource-2 Resource-3 M 1 3 5 None 5 0 3
| Activity | Estimated Duration (in weeks) | Preceding Activities | Required Reusable Resources | ||||
| Optimistic | Most Likely | Pessimistic | Resource-1 | Resource-2 | Resource-3 | ||
| M | 1 | 3 | 5 | None | 5 | 0 | 3 |
| N | 0.50 | 1 | 3 | None | 1 | 1 | 2 |
| P | 1 | 1 | 2 | None | 1 | 1 | 1 |
| Q | 2 | 3 | 6 | M | 2 | 0 | 3 |
| R | 1 | 3 | 4 | N | 1 | 0 | 0 |
| S | 1.50 | 2 | 2 | P | 4 | 2 | 2 |
| Maximum quantity of Reusable Resources available: | 5 | 2 | 3 | ||||
- Determine the Density (D ) of the project.
- Determine the Resource Utilization ( ) of the project.
- Compute the Project Network Complexity () value.
- What is the significance of D?
- What is the significance of ?
- What is the significance of ?
- What is the minimum number of Bench Marks this project must have?
- What is the sustainability level of this project?
- What type of complexity does this project network have?