Question: Activity Estimated Duration (in weeks) Preceding Activities Required Reusable Resources Optimistic Most Likely Pessimistic Resource-1 Resource-2 Resource-3 M 1 3 5 None 5 0 3

Activity

Estimated Duration (in weeks)

Preceding Activities

Required Reusable Resources

Optimistic

Most Likely

Pessimistic

Resource-1

Resource-2

Resource-3

M

1

3

5

None

5

0

3

N

0.50

1

3

None

1

1

2

P

1

1

2

None

1

1

1

Q

2

3

6

M

2

0

3

R

1

3

4

N

1

0

0

S

1.50

2

2

P

4

2

2

Maximum quantity of Reusable Resources available:

5

2

3

  1. Determine the Density (D ) of the project.
  2. Determine the Resource Utilization ( ) of the project.
  3. Compute the Project Network Complexity () value.
  4. What is the significance of D?
  5. What is the significance of ?
  6. What is the significance of ?
  7. What is the minimum number of Bench Marks this project must have?
  8. What is the sustainability level of this project?
  9. What type of complexity does this project network have?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!