Question: Activity Events (nodes) Times Start Finish Optimistic Most likely Pessimistic A 1 2 9 15 27 B 1 3 13 21 29 C 2 4

Activity Events (nodes) Times
Start Finish Optimistic Most likely Pessimistic
A 1 2 9 15 27
B 1 3 13 21 29
C 2 4 6 9 12
D 2 5 23 35 35
E 3 5 19 26 51
F 4 6 23 29 35
G 5 6 14 20 20
H 6 7 2 5 8
7. What are the estimated mean times for Activities A-H?
8. What are the estimated standard deviations in the times for Activities A-H?
9. What is the estimated mean time for project completion?
10. What are the estimated slack times for activities A-H?
11. What is the critical path for this project network?
12. What is the estimated standard deviation for the CRITICAL PATH completion time?
13. What is the probability that the critical path for this project will be completed within 75 days? 80 days? 85 days? 90 days?
14. Within what amount of time is there a 90% probability that the critical path for this project will be completed? 95% 99%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!