Question: Events (nodes) Times Activity Start Finish Optimistic Most Likely Pessimistic A 1 2 9 15 27 B 1 3 13 21 29 C 2 4

Events (nodes) Times

Activity Start Finish Optimistic Most Likely Pessimistic

A 1 2 9 15 27

B 1 3 13 21 29

C 2 4 6 9 12

D 2 5 23 35 35

E 3 5 19 26 51

F 4 6 23 29 35

G 5 6 14 20 20

H 6 7 2 5 8

What are the estimated mean times for activities A-H/

What are the estimated standard deviations in times for Activities A-H?