Question: activity expected cost activity duration Expected start date Expected completion date expected % complete Actual % complete Actual cost to date start up 100000 10
| activity | expected cost | activity duration | Expected start date | Expected completion date | expected % complete | Actual % complete | Actual cost to date |
| start up | 100000 | 10 days | 0 | 10 | 100% | 100% | 105000 |
| construction | 325000 | 14 days | 8 | 22 | 12/14=85.714 | 90% | 280000 |
| finishing | 50000 | 12 days | 18 | 30 | 2/12=16.667 | 25% | 2500 |
Exercise EVM Currently day 20 of the project Schedule variance = BCWP BCWS = ? Schedule performance index = BCWP/BCWS = ? Cost variance = BCWP AC = ? Cost performance index = BCWP / AC = ? Step by Step Solution