Question: activity expected cost activity duration Expected start date Expected completion date expected % complete Actual % complete Actual cost to date start up 100000 10

activity

expected

cost

activity

duration

Expected

start date

Expected

completion

date

expected %

complete

Actual %

complete

Actual cost to date
start up 100000 10 days 0 10 100% 100% 105000
construction 325000 14 days 8 22 12/14=85.714 90% 280000
finishing 50000 12 days 18 30 2/12=16.667 25% 2500
Exercise  EVM  Currently day 20 of the project  Schedule variance = BCWP  BCWS = ?  Schedule performance index = BCWP/BCWS = ?  Cost variance = BCWP  AC = ?  Cost performance index = BCWP / AC = ?