Question: Activity Expected Cost Expected % Complete Actual % Complete Actual Cost to Date A. Demolition $200,000 100% 100% $250,000 B. Foundation $800,000 100% 100% $1,250,000
| Activity | Expected Cost | Expected % Complete | Actual % Complete | Actual Cost to Date |
| A. Demolition | $200,000 | 100% | 100% | $250,000 |
| B. Foundation | $800,000 | 100% | 100% | $1,250,000 |
| C. Construction | $30,000,000 | 50% | 10% | $4,500,000 |
| Total | $31,000,000 | $6,000,000 |
a. BCWS =
b. BCWP =
c. Schedule Variance =
d. Cost Variance =
e. Is the project on schedule?
f. Is the project on budget?