Question: Activity Expected Cost Expected % Complete Actual % Complete Actual Cost to Date A. Demolition $200,000 100% 100% $250,000 B. Foundation $800,000 100% 100% $1,250,000

Activity

Expected

Cost

Expected % Complete

Actual %

Complete

Actual Cost

to Date

A. Demolition

$200,000

100%

100%

$250,000

B. Foundation

$800,000

100%

100%

$1,250,000

C. Construction

$30,000,000

50%

10%

$4,500,000

Total

$31,000,000

$6,000,000

a. BCWS =

b. BCWP =

c. Schedule Variance =

d. Cost Variance =

e. Is the project on schedule?

f. Is the project on budget?