Question: Activity Expected Expected % Complete Actual % Actual Cost Cost Complete to Date A. Demolition $200,000 100% 100% $250,000 B. Foundation $800,000 100% 100% $1,250,000

Activity Expected Expected % Complete Actual %

Activity Expected Expected % Complete Actual % Actual Cost Cost Complete to Date A. Demolition $200,000 100% 100% $250,000 B. Foundation $800,000 100% 100% $1,250,000 C. Construction $30,000,000 50% 10% $4,500,000 Total $31,000,000 $6,000,000 a. BCWS = b. BCWP = C. Schedule Variance d. Cost Variance = e. Is the project on schedule? f. Is the project on budget