Question: Activity Expected Duration (Days) Standard Deviation Predecessor(s) A 36.0 12.9 B 13.0 40.0 A 96.0 66.0 BD D 59.0 1.0 Compute the standard deviaiton of

Activity Expected Duration (Days) Standard
Activity Expected Duration (Days) Standard Deviation Predecessor(s) A 36.0 12.9 B 13.0 40.0 A 96.0 66.0 BD D 59.0 1.0 Compute the standard deviaiton of the critical path. Round your answer to 2 decimal places, if applicable, a