Question: Activity Expected Time (weeks) Immediate Predecessor(s) TIMO CD a. Choose the correct network diagram for this project. OA 0 0 0 Start Finish Start OOO

Activity Expected Time (weeks) Immediate

Activity Expected Time (weeks) Immediate Predecessor(s) TIMO CD a. Choose the correct network diagram for this project. OA 0 0 0 Start Finish Start OOO OOS D 0 0 0 Start Finish b. Identify the critical path and estimate the project's duration The critical path is path B-D-F and the project duration is 15 weeks. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Activity (weeks)