Question: Activity Expected Time (weekweeks) Immediate Predecessor(s) A 33 long dash B 22 long dash C 22 A D 33 B E 55 C, D F
| Activity | Expected Time (weekweeks) | Immediate Predecessor(s) |
| A | 33 | long dash |
| B | 22 | long dash |
| C | 22 | A |
| D | 33 | B |
| E | 55 | C, D |
| F | 66 | D |
Calculate the slack for each activity.