Question: Activity Normal Time ( weeks ) Crash Time ( weeks ) Normal Cost Crash Cost Immediate Predecessor ( s ) A 3 3 2 2

Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Crash Cost
Immediate Predecessor(s)
A
33
22
$ 1 comma 200$1,200
$ 1 comma 850$1,850
long dash
B
22
11
$ 2 comma 000$2,000
$ 2 comma 700$2,700
long dash
C
11
11
$ 400$400
$ 400$400
long dash
D
77
33
$ 1 comma 500$1,500
$ 1 comma 820$1,820
A
E
66
33
$ 950$950
$ 1 comma 250$1,250
B
F
22
11
$ 4 comma 000$4,000
$ 5 comma 200$5,200
C
G
44
22
$ 1 comma 500$1,500
$ 2 comma 100$2,100
D, E
Part 2
a) Based on the given information regarding the activities for the project, the project completion dateequals=3333 weeks.
Part 3
b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing LOADING... the activities.
Part 4
The first activity to crash is
A
A
C
E
B
F
G
D
by 22 weeks at a per week crashing cost of 650650 dollars.
Part 5
Next, one should crash activity D and activity
G
B
F
A
E
C
D
G
by 22 weeks for an additional total per week crashing cost of enter your response here dollars.
Part 6
c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, the following is the order for crashing.
Part 7
The next activity to crash in order is
G
E
D
C
A
B
F
by 22 weeks at a per week crashing cost of enter your response here dollars.
Part 8
Next, one should crash activity
A
B
C
D
E
F
G
and activity E by 11 week at a total per week crashing cost of enter your response here dollars.
Part 9

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!