Question: Activity Flow Time Preceding Task A 10 min None B 6 min A C 12 min A D 8 min B E 4 min C
| Activity | Flow Time | Preceding Task |
| A | 10 min | None |
| B | 6 min | A |
| C | 12 min | A |
| D | 8 min | B |
| E | 4 min | C |
| F | 5 min | D, E |
a. Given the following information for a process, the process flow time would be:
b. What is the critical path?
c. If activity D is crashed by 3 minutes, what is the process flow time? Explain.
d. If activity C is crashed by 3 minutes, what is the process flow time? Explain.