Question: Activity ID Precedent Activity DURATION (IN WEEKS) Optimistic Most Likely Pessimistic Expected A - 10 22 22 B - 20 20 20 C - 4
| Activity ID | Precedent Activity | DURATION (IN WEEKS) | |||
|
|
| Optimistic | Most Likely | Pessimistic | Expected |
| A | - | 10 | 22 | 22 |
|
| B | - | 20 | 20 | 20 |
|
| C | - | 4 | 10 | 16 |
|
| D | A | 2 | 14 | 32 |
|
| E | B; C | 8 | 8 | 20 |
|
| F | B; C | 8 | 14 | 20 |
|
| G | D; C | 4 | 4 | 4 |
|
| H | C | 2 | 12 | 16 |
|
| I | G; H | 6 | 16 | 38 |
|
| J | D; E | 2 | 8 | 14 |
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts