Question: Activity ( - ies ) F is ( are ) on all paths. Part 1 0 c . The critical activities are C , E

Activity(-ies)
F
is(are) on all paths.
Part 10
c. The critical activities are
C, E, F, and G
, so they make up the critical path.
Part 11
The entire project will take
23.5 days to complete. (Enter your response rounded to one decimal place.)
Part 12
d. Every day the project goes on costs the company $8 comma 000 in overhead costs. One of the managers responsible for carrying out activity Upper A feels she can crash the activity by 1 day through the use of overtime. The cost would be only $3 comma 500. Should the company do it?
A.
No, because crashing cost is more than the daily project's cost.
B.
Yes, because the total project time will be reduced by 1 day.
C.
Yes, because crashing cost is less than the daily project's cost.
D.
No, because activity Upper A is not on the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!