Question: Activity Immediate Optimistic Mean Pessimistic Predecessor Time Time With the data from the table: Time A 3 5 . Draw the network diagram 6 .

 Activity Immediate Optimistic Mean Pessimistic Predecessor Time Time With the data

Activity Immediate Optimistic Mean Pessimistic Predecessor Time Time With the data from the table: Time A 3 5 . Draw the network diagram 6 . Identify the critical path B 4 5 8 . Estimate the estimated time to C A 5 6 7 completion using the PERT D A 1 2 formula 4 E C, B If project must be completed in 2 4 I 5 18 months. Do you anticipate C, B 1 3 5 difficulty in meeting the G D, E 4 deadline? 6 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!