Question: Activity Immediate Optimistic Most Pessimistic Standard Variance Predecessor Likely Deviation A -- 4 5 6 0.333 0.111 B -- 12 15 18 1 1 C
| Activity | Immediate | Optimistic | Most | Pessimistic | Standard | Variance |
| Predecessor | Likely | Deviation | ||||
| A | -- | 4 | 5 | 6 | 0.333 | 0.111 |
| B | -- | 12 | 15 | 18 | 1 | 1 |
| C | A | 2 | 8 | 14 | 2 | 4 |
| D | A | 5 | 5 | 5 | 0 | 0 |
| E | B, C | 6 | 7 | 8 | 0.333 | 0.111 |
| a) | Which activities are on the critical path? | ||||
| b) | compute the slack time for activity E | ||||
| c) | What is the completion time and variance of the critical path? | ||||
| d) | Which activity has the most slack? | ||||
| e) | Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. What is the probability that the project is finished in 24 weeks or fewer? (Round to two decimals.) | ||||
| f) | what is the latest possible time that C may be started without delaying completion of the project? | ||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
