Question: Activity Immediate Predecessor Optimistic Most Likely Pessimistic Standard Deviation Variance A -- 4 5 6 0.333 0.111 B -- 12 16 18 1.000 1.000 C

Activity

Immediate

Predecessor

Optimistic

Most

Likely

Pessimistic

Standard

Deviation

Variance

A

--

4

5

6

0.333

0.111

B

--

12

16

18

1.000

1.000

C

A

2

8

14

2.000

4.000

D

A

5

5

5

0.000

0.000

E

B, C

6

7

8

0.333

0.111

Which activities in this five activity PERT project are on the critical path?

a.A-B-C-D

b. A-C-E

c. B-E

d. B-D