Question: Activity Immediate Predecessor Optimistic Most Likely Pessimistic Standard Deviation Variance A -- 4 5 6 0.333 0.111 B -- 12 16 18 1.000 1.000 C
|
Activity | Immediate Predecessor | Optimistic | Most Likely | Pessimistic | Standard Deviation | Variance |
| A | -- | 4 | 5 | 6 | 0.333 | 0.111 |
| B | -- | 12 | 16 | 18 | 1.000 | 1.000 |
| C | A | 2 | 8 | 14 | 2.000 | 4.000 |
| D | A | 5 | 5 | 5 | 0.000 | 0.000 |
| E | B, C | 6 | 7 | 8 | 0.333 | 0.111 |
Which activities in this five activity PERT project are on the critical path?
a.A-B-C-D
b. A-C-E
c. B-E
d. B-D