Question: Activity Immediate optimistic Pessimistic Estimated Variance predecessor time (a) time (b) 6 activities TE time (days) ((b-a)/6) A 14 20 116 B 10 118 14

Activity Immediate optimistic Pessimistic Estimated Variance predecessor time (a) time (b) 6 activities TE time (days) ((b-a)/6) A 14 20 116 B 10 118 14 A, B 15 BO 18 B 8 116 12 E 8 112 10 D 8 8 8 G CE 4 10 6 H G B 9 15 HF 6 14 9 Calculate the estimated duration of finishing the project within 95% certainty