Given the schedule in the following table for a software development project: Attach your answer in...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Given the schedule in the following table for a software development project: Attach your answer in handwritten format with the permitted types of files. Activity immediate Optimistic Pessimistic Estimated Variance time (b) predecessor time (a) activities time (days) (b-a)/6)² TE A. 14 20 16 B 10 18 14 A B 15 30 18 18 16 12 IE B 18 12 10 IF ID 18 8 IG C, E 10 6 15 H, F 14 19 Calculate the estimated duration of finishing the project within 95% certainty? STANDARD NORMAL DISTRIBUTION: Table Values Represent AREA to the LEFT of the Z seore. 00 02 50798 .03 51197 05 06 52392 07 52790 .08 53188 .04 .09 0.0 50000 50399 51595 51994 53586 0.1 53983 54380 54776 55172 55567 55962 56356 56749 57142 57535 0.2 57926 58317 58706 5909S 59483 59871 ,60257 60642 61026 61409 0.3 61791 62172 62552 62930 63307 63683 64058 64431 64803 65173 67364 70884 67724 71226 0.4 65542 69146 65910 69497 66276 69847 66640 67003 68082 71566 68439 .71904 68793 72240 0.5 70194 70540 0.6 .72575 72907 73237 73565 .73891 74215 74537 74857 75175 75490 0.7 75804 76115 76424 76730 77035 .77337 .77637 .77935 78230 78524 0.8 .78814 79103 79389 79673 79955 80234 80511 80785 81057 81327 81594 82121 82381 82639 85083 83147 83398 83646 85993 0,9 81859 82894 85314 83891 86214 1.0 84134 84375 84614 84849 85543 85769 1.1 86433 86650 86864 87076 87286 87493 87698 87900 88100 88298 8. co co 3. Given the schedule in the following table for a software development project: Attach your answer in handwritten format with the permitted types of files. Activity immediate Optimistic Pessimistic Estimated Variance time (b) predecessor time (a) activities time (days) (b-a)/6)² TE A. 14 20 16 B 10 18 14 A B 15 30 18 18 16 12 IE B 18 12 10 IF ID 18 8 IG C, E 10 6 15 H, F 14 19 Calculate the estimated duration of finishing the project within 95% certainty? STANDARD NORMAL DISTRIBUTION: Table Values Represent AREA to the LEFT of the Z seore. 00 02 50798 .03 51197 05 06 52392 07 52790 .08 53188 .04 .09 0.0 50000 50399 51595 51994 53586 0.1 53983 54380 54776 55172 55567 55962 56356 56749 57142 57535 0.2 57926 58317 58706 5909S 59483 59871 ,60257 60642 61026 61409 0.3 61791 62172 62552 62930 63307 63683 64058 64431 64803 65173 67364 70884 67724 71226 0.4 65542 69146 65910 69497 66276 69847 66640 67003 68082 71566 68439 .71904 68793 72240 0.5 70194 70540 0.6 .72575 72907 73237 73565 .73891 74215 74537 74857 75175 75490 0.7 75804 76115 76424 76730 77035 .77337 .77637 .77935 78230 78524 0.8 .78814 79103 79389 79673 79955 80234 80511 80785 81057 81327 81594 82121 82381 82639 85083 83147 83398 83646 85993 0,9 81859 82894 85314 83891 86214 1.0 84134 84375 84614 84849 85543 85769 1.1 86433 86650 86864 87076 87286 87493 87698 87900 88100 88298 8. co co 3.
Expert Answer:
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Posted Date:
Students also viewed these computer network questions
-
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and...
-
Your portfolio had the values in the following table for the 4 years listed. Calculate your average return over the 4-year period. Beginning Value ($) 50,000.00 55,000.00 58,000.00 65,000.00 Year...
-
Given the schedule in the following table for a software development project: Attach your answer in handwritten format with the permitted types of files. Activity mmediate Optimistic predecessor time...
-
QUESTION 5 Discuss the difference between the following:(a) Functional & non-functional requirements(b) User & system requirements T T T Arial ABC 3 (12pt) T Path: p Words:0
-
For the data for year 2003 in Exercise 7 in this section, construct a histogram, a frequency polygon, and an give, using relative frequencies.
-
Use the data for Langley Inc. in exercise 5-14 to answer the following {Requirements} 1. Compute cost of goods sold and ending inventory, using each of the following methods: a. Specific unit cost,...
-
Assume HPC, Inc., began December with 60 units of inventory that cost a total of $720. During December, HPC, Inc., purchased and sold goods as follows: HPC, Inc., uses perpetual inventory. Under the...
-
Sea Ventures manufactures goods on a job order basis. During the month of June, three jobs were started in process. (There was no work in process at the beginning of the month.) Jobs Racers and...
-
The Court of Appeal overturned the decision of the trial judge and found: Mr Finch could not claim for his psychiatric injury, applying the test set out in Alcock v Chief Constable of South Yorkshire...
-
A simple ac generator consists of a coil with 10 turns (each turn has an area of 50 cm2). The coil rotates in a uniform magnetic field of 350 mT with a frequency of 60 Hz. (a) Write an expression in...
-
You only need to show the "formal proof" in answering the following questions. n if n 100 3 if n > 100 n i. Show that limnoo an = 0 where an = ii. Show that limno 2n - 5n - 2 n - 5 = 0.
-
The heat transfer coefficient for hydrogen flowing over a sphere is to be determined by observing the temperature-time history of a sphere fabricated from pure copper. The sphere, which is \(20...
-
A copper sheet of thickness \(2 L=2 \mathrm{~mm}\) has an initial temperature of \(T_{i}=118^{\circ} \mathrm{C}\). It is suddenly quenched in liquid water, resulting in boiling at its two surfaces....
-
A dormitory at a large university, built 50 years ago, has exterior walls constructed of \(L_{s}=30\)-mm-thick sheathing with a thermal conductivity of \(k_{s}=0.1 \mathrm{~W} / \mathrm{m} \cdot...
-
In a manufacturing process, a spherical ceramic particle of diameter \(D=300 \mu \mathrm{m}\) and initial temperature \(T_{i}=1100 \mathrm{~K}\) is injected into a chamber containing a hot gas stream...
-
Why is the adjusted present value (APV) method preferred to the cost of capital adjustment (CCA) method in valuing international projects?
-
Because your demand has an upward trend, you want to use a forecast including a trend. In period 18, the level is estimated at F18 = 5,520, and the trend is estimated at T18 = 40. These give you FIT...
-
The cost curve for the city water supply is C(Q) = 16 + 1/4 Q2, where Q is the amount of water supplied and C(Q) is the cost of providing Q acre-feet of water. (An acre-foot is the amount of water...
-
Can risk analysis be used for nonproject business decision making? Explain how.
-
How can an auditor/evaluator avoid the shortfalls described in the article? MINI CASE Overall, in the light of this study, we would come out strongly in favor of post-project reviews (provided you do...
-
What should Mr. Rutland do? Include the following issues: Budget: acquiring adequate resources Philanthropic organizations Governmental agencies Donations Memberships Visitors Budget:...
-
The ends of a beam are elastically restrained by linear and torsional springs, as shown in Fig. 11.11. Using the finite difference method, express the boundary conditions. k W(x) k 00000 Deflected...
-
Find the natural frequencies of a fixed-fixed bar undergoing longitudinal vibration, using three mesh points in the range \(0
-
Using the fourth-order Runge-Kutta method, solve Problem 11.20. Data From Problem 11.20:- The equations of motion of a two-degree-of-freedom system are given by \(2 \ddot{x}_{1}+6 x_{1}-2 x_{2}=5\)...
Study smarter with the SolutionInn App