Question: Activity immediate predecesors duration crash cost per week minimum task duration A N/a 6 n/a 6 B a 19 5000 17 C a 5 n/a

Activity immediate predecesors duration crash cost per week minimum task duration

A

N/a 6 n/a 6
B a 19 5000 17
C a 5 n/a 5
D c 2 1500 1
E c 6 1000 3
F d,e 6 3000 5
G f 1 n/a 1

A) Draw the project network and list ES, EF, LS, LF and duration for each task

B) list tasks on critical path

C) what is expected project duration in weeks

D) what is the slack for each activity

E) crash by 2 weeks. What are the best activities to crash and what is the resulting total crash cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!