Question: Activity Immediate Predecessor a ( days ) m ( days ) b ( days ) A - 2 5 8 B - 3 6 9

Activity Immediate Predecessor a (days) m (days) b (days)
A -258
B -369
C A 4710
D B 2514
E C 333a) What is the expected completion time for this project?
b) What variance value would be used in finding possibilities of finishing by a certain time?
c) What is a probability if the project time exceed 2 days after completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!