Question: Activity Immediate Predecessor a ( days ) m ( days ) b ( days ) A - 2 5 8 B - 3 6 9
Activity Immediate Predecessor a days m days b days
A
B
C A
D B
E C a What is the expected completion time for this project?
b What variance value would be used in finding possibilities of finishing by a certain time?
c What is a probability if the project time exceed days after completion time?