Question: The project described by: Activity Immediate Predecessor Time (days) A -- 6 B A 2 C -- 8 D B, C 5 E D 7
The project described by:
| Activity | Immediate Predecessor | Time (days) |
| A | -- | 6 |
| B | A | 2 |
| C | -- | 8 |
| D | B, C | 5 |
| E | D | 7 |
has a critical path of length of
|
| C) 17 days. |
|
| A) 15 days. |
|
| D) 18 days. |
|
| E) None of the above |
|
| B) 20 days. |