Question: Activity Immediate Predecessor Current time (days) Cost to complete one day faster A - 9 2 B - 5 1 C A 4 can't get

Activity

Immediate Predecessor

Current

time (days)

Cost to complete one day faster
A - 9 2
B - 5 1
C A 4 can't get done faster
D B,C 10 4
E D 9 can't get done faster
F E 4 3

What is the current project completion time using the current times (days)? (Enter "5" if completion time is 5 days.)

What would be the minimum cost associated with completing the project one day faster than with the current times?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!