Question: Activity Immediate Predecessor Current time (days) Cost to complete one day faster A - 9 2 B - 5 1 C A 4 can't get
|
Activity |
Immediate Predecessor | Current time (days) | Cost to complete one day faster |
| A | - | 9 | 2 |
| B | - | 5 | 1 |
| C | A | 4 | can't get done faster |
| D | B,C | 10 | 4 |
| E | D | 9 | can't get done faster |
| F | E | 4 | 3 |
What is the current project completion time using the current times (days)? (Enter "5" if completion time is 5 days.)
What would be the minimum cost associated with completing the project one day faster than with the current times?