Question: Problem 2 Activity Immediate Predecessor Normal Time (Days) Normal Cost ($) Crash Time (Days) Crash Cost ($) A ------- 12 5,000 10 9,000 B -------

Problem 2

Activity

Immediate

Predecessor

Normal

Time (Days)

Normal

Cost ($)

Crash

Time (Days)

Crash

Cost ($)

A

-------

12

5,000

10

9,000

B

-------

10

4,000

8

6,000

C

A

14

6,000

12

7,000

D

B

8

3,000

6

4,000

E

A, B

9

5,000

9

5,000

(a) Draw the Precedence Diagram for the above project, complete with ES, EF, LS, and LF.

Answer:

First draw the network on a separate sheet of paper and then fill the following table:

Activity

Immediate

Predecessor

Normal Time

ES

EF

LS

LF

Slack

Critical

Path?

A

-------

12

B

-------

10

C

A

14

D

B

8

E

A, B

9

(b) What is the Critical Path?

Answer:

Critical Path:

(c) What is the Project Completion Time under normal schedule?

Answer:

Project Completion Time;

(d) If the total project time has to be crashed by TWO days, which activity will you choose and what is the extra cost?

Answer:

Activity to be Crashed:

Extra Cost:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!