Question: ACTIVITY IMMEDIATE PREDECESSOR DURATION (Days) a m b A - 8 10 12 B - 6 7 9 C - 3 3 4 D A
| ACTIVITY | IMMEDIATE PREDECESSOR | DURATION (Days) a m b |
| A | - | 8 10 12 |
| B | - | 6 7 9 |
| C | - | 3 3 4 |
| D | A | 10 20 30 |
| E | C | 6 7 8 |
| F | B,D,E | 9 10 11 |
| G | B,D,E | 6 7 10 |
| H | F | 14 15 16 |
| I | F | 10 11 13 |
| J | G,H | 6 7 8 |
| K | I,J | 4 7 8 |
| L | G,H | 1 2 4 |
d) What is the probability of the project being between 50 and 70 days?
e) What is the expected completion time at the 68%, 94% and 99% probability of completion?