Question: ACTIVITY IMMEDIATE PREDECESSOR DURATION (Days) a m b A - 8 10 12 B - 6 7 9 C - 3 3 4 D A

ACTIVITY

IMMEDIATE PREDECESSOR

DURATION (Days)

a m b

A

-

8 10 12

B

-

6 7 9

C

-

3 3 4

D

A

10 20 30

E

C

6 7 8

F

B,D,E

9 10 11

G

B,D,E

6 7 10

H

F

14 15 16

I

F

10 11 13

J

G,H

6 7 8

K

I,J

4 7 8

L

G,H

1 2 4

d) What is the probability of the project being between 50 and 70 days?

e) What is the expected completion time at the 68%, 94% and 99% probability of completion?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!