Question: Q3. (35 pts) Consider the below activity table for a project. Activity Immediate Predecessor Duration (days) A 8 B A 4 C BE 2 D

Q3. (35 pts) Consider the below activity table

Q3. (35 pts) Consider the below activity table for a project. Activity Immediate Predecessor Duration (days) A 8 B A 4 C BE 2 D 10 E H 8 F 2 G A 14 H 6 I F 2 Calculate the Critical Chain. Resource Green Purple Orange Red Purple Orange Blue Black Orange (Note: if you end up having decimal numbers for the buffers, please round them up to next integer number.) If you want, you can use the below diagram (copy/paste if you need more) when calculating the critical chain schedules. 0 1 2 3 6 9 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!