Question: Activity Immediate Predecessor Duration (days) Start A B C D E F QUESTION 16 G H Start End F H Start D a. AEFG O

Activity Immediate Predecessor Duration (days)

Activity Immediate Predecessor Duration (days) Start A B C D E F QUESTION 16 G H Start End F H Start D a. AEFG O b. ABCDE O C. DEGHC O d. ACGH D & A E & F G 3 4 7 4 9 8 4 B, C Given the above activities, predecessors, and duration, draw a network diagram on the paper and answer the questions (you don't have to submit the diagram). What is the critical path? (Write the letters in the proper order) 2 6 points Save