Question: Activity Immediate Predecessor Duration (days) Start A Start 3 B F 4 C H 7 D Start 4 E D 9 F D & A

  1. Activity Immediate Predecessor Duration (days)

    Start

    A Start 3

    B F 4

    C H 7

    D Start 4

    E D 9

    F D & A 8

    G E & F 4

    H G 2

    End B, C

    Given the above activities, predecessors, and duration, draw a network diagram on the paper and answer the questions (you don't have to submit the diagram).

    What is the critical path? (Write the letters in the proper order)

    a.

    AEFG

    b.

    ABCDE

    c.

    DEGHC

    d.

    ACGH

What's the duration of the project (use the diagram created).

a.

28 days

b.

26 days

c.

25 days

d.

27 days

If activity B will take 6 days how it will affect the project? (use the diagram you have created).

a.

Project will take longer to compete.

b.

Project duration remains the same

c.

Project will be completed earlier.

d.

Critical path will change.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!