Question: Activity Immediate Predecessor Duration (months) A None 2 B A 4 C A 2 D B 2 E B, C 4 F A, E 6
| Activity | Immediate Predecessor | Duration (months) |
| A | None | 2 |
| B | A | 4 |
| C | A | 2 |
| D | B | 2 |
| E | B, C | 4 |
| F | A, E | 6 |
| G | D | 4 |
| H | D, E, F | 2 |
| I | G, H | 6 |
| J | H, F | 6 |
| K | H, I, J | 4 |
What is the free float for activity E with respect to activity H? Show your calculations