Question: Activity Immediate Predecessor Duration (months) A NONE 2 B A 4 C A 2 D B 2 E B,C 4 F A,E 6 G D
| Activity | Immediate Predecessor | Duration (months) |
| A | NONE | 2 |
| B | A | 4 |
| C | A | 2 |
| D | B | 2 |
| E | B,C | 4 |
| F | A,E | 6 |
| G | D | 4 |
| H | D,E,F | 2 |
| I | G,H | 6 |
| J | H,F | 6 |
| K | H,I,J | 4 |
4.1 Construct a network diagram to visually illustrate the project tasks. (18)
4.2. What is the project duration (2)
(PROJECT MANAGEMENT 2)